Five new shift buses arrived at the motor depot of LLC "InterRegionConstruction" in Novy Urengoy for further transportation of employees to the facilities of "Payakha MPS - North Bay Port Oil Pipeline" and "Vankor - Suzun Oil Pipeline".
The process of concreting of filling the intertube space of the leader wells continues, and static tests of soils with piles are underway at the facility "Payakha MPS - North Bay Port Oil Pipeline".
n 29 November 2023, the representative of LLC "InterRegionConstruction", the Engineer of Production and Technical Department Vasily Krotkov took part in the extended meeting of the Council of Young Specialists of the Moscow Urban Planning Policy and Construction Complex.
LLC "InterRegionConstruction" is finishing work on dumping of Site No. 6 at the facility of Krasnogorsk Water Lifting Hydroelectric Power Plant on the Irtysh River. Work completion. Start-up complex (Stage 1 of construction).
LLC "InterRegionConstruction" performs a range of works on pile fabrication, installation of finished pile products at the linear part of the Payakha North Bay oil pipeline: drilling, immersion, filling of cavities and pile body.