May is the month when the Construction and Installation Department summarizes the results. Three months ago, the first team of workers from Construction and Installation Department No. 1, led by Taras Andreevich Batrakov, landed to participate in the development of the Tagulskoye field and the Vankor—Suzun oil pipeline in the Krasnoyarsk region.
The team of Construction and Installation Department No. 1 has extensive experience in construction and development of oil and gas fields (such as Bovanenkovskoye, Yubileynoye, Chayandinskoye, Zapolyarnoye, etc.). This factor became the cornerstone of the "credit of trust" extended to the Department by the company's leadership, which facilitated the efficient organization of work processes and helped overcome numerous challenges encountered at the initial stages.
This is clearly illustrated by the development dynamics of Construction and Installation Department No. 1. Whereas in March 2024 its total staff did not exceed 10 persons, currently the number of personnel has increased to 160 people.
To date, Construction and Installation Department No. 1 participates in the construction of the following objects:
1. Development of the Tagulskoye field. Well pad No. 24 with utility corridors.
2. Development of the Tagulskoye field. Well pad No. 30 with utility corridors.
3. Development of the Tagulskoye field. Oil treatment unit
with a pipeline to the tie-in point in the Vankor—Purpe trunk oil pipeline.
4. Vankor—Suzun—Payakha oil transportation system. Vankor—Suzun oil pipeline.
5. Technological berth in Kamchatka Krai.
During the past production period, the total volume of work completed by the Department for the specified projects amounted to:
Vankor production site:
1. Piles manufactured: 459 pcs.
2. Over 2,950 caps have been installed.
3. Over 1,400 footings for supports have been installed.
4. Over 1,400 supports have been installed.
Tagul production site:
1. Mechanical cleaning and anti-corrosion protection of piles covering an area exceeding 300 м2 has been completed.
2. Completed full repair of insulation joints for water pipeline Ø168 and oil pipeline Ø273, totaling 320 joints.
3. Thermally insulated 458 joints of the Ø426 Vankor—Purpe oil pipeline (entire project scope).
4. To date, thermal insulation of the Ø426 oil pipeline joints from Well Pad No. 26 to Well Pad No. 24 is being carried out, where more than 100 joints have been insulated.
Construction project in Kamchatka:
1. K1 reinforcement frames manufactured: 46 pcs.
2. Manufactured over 19,200 reinforcement parts.
3. CT tables manufactured/assembled: 23/61 pcs.
4. B1-B5 girders manufactured/assembled: 25/7 pcs.
5. Assembly and installation of modular dormitories for personnel accommodation and construction headquarters is in progress.
At the same time, the scope of works being carried out by the Department covers the entire spectrum of construction activities, ranging from pile fabrication to pipeline insulation works.
Given the tight construction deadlines, the Construction and Installation Department faces a challenging task of increasing capital investment utilization by more than three times compared to previous periods. With the main resource of any construction site being a highly skilled team of workers, there is no doubt that the Construction and Installation Department will achieve the planned targets with maximum efficiency.